It remains one of the landmark construction law cases. [1] The owner impliedly warrants the information, plans and specifications which an owner provides to a general contractor. The contractor will not be liable to the owner for loss or damage which results solely from insufficiencies or defects in such information, plans and specifications. [2]
To decide whether to apply federal law, Justice Kennedy applied a two-part test from Lugar v. Edmondson Oil Co. [4] The first part of the test is whether the constitutional deprivation, in this case the right to a fair and impartial jury, resulted from a right rooted in state authority. Kennedy found, almost summarily, that peremptory ...
Ruxley Electronics and Construction Ltd v Forsyth [1995] UKHL 8 is an English contract law case, concerning the choice between an award of damages for the cost of curing a defect in a building contract or (when that is unreasonable) for awarding damages for loss of "amenity".
In the court case S.J. Amoroso Construction Co. v. U.S., 26 Cl. Ct. 759 (1992), Judge Plager wrote an opinion suggesting that the court had used the Christian Doctrine to resolve a case that could have been resolved more satisfactorily using other legal principles. He argued for very limited use of the Christian Doctrine based on the following ...
This decision by the Supreme Court to not allow exemptions confirmed that Section 7 of the Endangered Species Act was a strong substantive provision and helped shape federal environmental law. [2] The case is commonly cited as an example of the strict construction-plain meaning canon of construction, and the equitable principle that courts ...
Construction law builds upon general legal principles and methodologies and incorporates the regulatory framework (including security of payment, planning, environmental and building regulations); contract methodologies and selection (including traditional and alternative forms of contracting); subcontract issues; causes of action, and liability, arising in contract, negligence and on other ...
Chartbrook Ltd v Persimmon Homes Ltd [2009] UKHL 38 is an English contract law case concerning interpretation of contracts.It creates a so-called "red ink" rule, that there is no limit to verbal rearrangement that the court may deploy to give a commercial sensible meaning when construing a contract in its bargaining context.
Karsales (Harrow) Ltd v Wallis [1956] EWCA Civ 4 is an English Court of Appeal decision which established fundamental breach as a major English contract law doctrine. Denning LJ MR gave the leading judgment replacing the Rule of Strict Construction, which require a literal approach to the construction of contract terms.