Search results
Results from the WOW.Com Content Network
Nuclear-power stocks fell after regulators voted against a deal between Amazon and Talen Energy. The deal would permit a Talen nuclear plant to provide an Amazon data center with extra power.
Building data centers on power plant sites, in an arrangement known as co-location, gives Big Tech a fast track to access large amounts of electricity to expand data centers instead of waiting
The Federal Energy Regulatory Commission on Friday rejected an agreement to increase the power capacity of an Amazon data center connected directly to Talen Energy's nuclear power plant in ...
The plans come as the owner of the shuttered Three Mile Island nuclear power plant said last month it plans to restart the reactor so tech giant Microsoft can buy the power to supply its data centers. All three companies have been investing in solar and wind technologies, which make electricity without producing greenhouse gas emissions.
It said Exelon refused to complete interconnection work at the LaSalle nuclear plant in Illinois for a new co-located data center. Constellation said the refusal could cost it $15 million to $19 ...
The grid operator PJM Interconnection and the Susquehanna, Pennsylvania, plant (which Talen owns), had asked to increase the amount of power going to the Amazon data center from 300 megawatts (MW ...
U.S. energy regulators rejected an amended interconnection agreement for an Amazon data center connected directly to a nuclear power plant in Pennsylvania, a filing showed on Friday. Members of ...
NEW YORK (Reuters) -Talen Energy has asked U.S. regulators to reject a challenge to its recent Amazon data center deal, which is being opposed by a group of electric utilities that say the ...