A cost estimate is the approximation of the cost of a program, project, or operation. The cost estimate is the product of the cost estimating process. The cost estimate has a single total value and may have identifiable component values. A problem with a cost overrun can be avoided with a credible, reliable, and accurate cost estimate. A cost ...
The most basic element of a cost estimate and therefore the cost database is the estimate line item or work item. [3] An example is "Concrete, 4000 psi (30 MPa)," which is the description of the item. In the cost database, an item is a row or record in a table (of items) and the description is a column or field for that record.
A cost estimator will typically use estimating software to estimate their bid price for a project, which will ultimately become part of a resulting construction contract. Some architects, engineers, construction managers, and others may also use cost estimating software to prepare cost estimates for purposes other than bidding such as budgeting ...
Cost estimation models are mathematical algorithms or parametric equations used to estimate the costs of a product or project. The results of the models are typically necessary to obtain approval to proceed, and are factored into business plans, budgets, and other financial planning and tracking mechanisms.
A Allocation of costs is the transfer of costs from one cost item to one or more other cost items. Allowance - a value in an estimate to cover the cost of known but not yet fully defined work. As-sold estimate - the estimate which matches the agreed items and price for the project scope. B Basis of estimate (BOE) - a document which describes the scope basis, pricing basis, methods ...
Cost engineering is "the engineering practice devoted to the management of project cost, involving such activities as estimating, cost control, cost forecasting, investment appraisal and risk analysis". [1] "Cost Engineers budget, plan and monitor investment projects.
The U.S. Government Accountability Office defines a cost estimate as, "the summation of individual cost elements, using established methods and valid data, to estimate the future costs of a program, based on what is known today", and reports that "realistic cost estimating was imperative when making wise decisions in acquiring new systems". [7]
Basis of estimate (BOE) is a tool used in the field of project management by which members of the project team, usually estimators, project managers, or cost analysts, calculate the total cost of the project.