Search results
Results from the WOW.Com Content Network
Maximum Demand Indicator (MDI) is an instrument for measuring the maximum amount [clarification needed] of electrical energy required by a specific consumer during a given period of time. [1] MDI instruments record the base load requirement of electrical energy .
The transformers are usually rated at 5 kVA, 10 kVA, and 25 kVA. The load densities are usually below 0.5 kVA per kilometer (0.8 kVA per mile) of line. Any single customer's maximum demand will typically be less than 3.5 kVA, but larger loads up to the capacity of the distribution transformer can also be supplied.
In a power system, a load curve or load profile is a chart illustrating the variation in demand/electrical load over a specific time. Generation companies use this information to plan how much power they will need to generate at any given time. A load duration curve is similar to a load curve. The information is the same but is presented in a ...
MSP kWh is the amount of electricity consumed at the 'meter supply point', which is the customer's meter. GSP kWh is obtained by multiplying the MSP kWh by the Line Loss Factor (LLF, a figure > 1) to include the amount of electricity lost when it is conducted through the distribution network, from the 'grid supply point' to the customer's meter.
The unofficial term diversity, as distinguished from diversity factor, refers to the percent of time available that a machine, piece of equipment, or facility has its maximum or nominal load or demand; a 70% diversity means that the device in question operates at its nominal or maximum load level 70% of the time that it is connected and turned on.
For example, if the load power factor were as low as 0.7, the apparent power would be 1.4 times the real power used by the load. Line current in the circuit would also be 1.4 times the current required at 1.0 power factor, so the losses in the circuit would be doubled (since they are proportional to the square of the current).
The theoretical maximum energy output of a given installation is defined as that due to its continuous operation at full nameplate capacity over the relevant period. The capacity factor can be calculated for any electricity producing installation, such as a fuel consuming power plant or one using renewable energy , such as wind, the sun or ...
One of the major issues with the real-time unit commitment problem is the fact that the electricity demand of the transmission network is usually treated as a "load point" at each distribution system. The reality, however, is that each load point is a complex distribution network with its own sub-loads, generators, and DERs. By simplifying a ...