Activity diagrams [1] are graphical representations of workflows of stepwise activities and actions [2] with support for choice, iteration, and concurrency. In the Unified Modeling Language, activity diagrams are intended to model both computational and organizational processes (i.e., workflows), as well as the data flows intersecting with the related activities.
An activity diagram, with the activity "Cooking Spaghetti" outlined with an "Activity frame" An activity in Unified Modeling Language (UML) is a major task that must take place in order to fulfill an operation contract. The Student Guide to Object-Oriented Development defines an activity as a "sequence of activities that make up a process."
The ACD is a modeling tool that was developed in 1960 following the flow diagram method of K.D. Tocher. [2] It pertains to the activity-based paradigm of system modeling, as opposed to process-oriented or event-based paradigms.
It emphasizes what must happen in the system being modeled. Since behavior diagrams illustrate the behavior of a system, they are used extensively to describe the functionality of software systems. As an example, the activity diagram describes the business and operational step-by-step activities of the components in a system.
Although the activity-on-arrow diagram (PERT chart) is still used in a few places, it has generally been superseded by the activity-on-node diagram, where each activity is shown as a box or node and the arrows represent the logical relationships going from predecessor to successor as shown here in the "Activity-on-node diagram". Activity-on ...
In addition, other behavioral UML diagrams such as activity diagrams, sequence diagrams, communication diagrams, and state machine diagrams can also be used to visualize use cases accordingly. Specifically, a System Sequence Diagram (SSD) is a sequence diagram often used to show the interactions between the external actors and the system under ...
By drawing the activities parallel in the diagram, connected with a synchronization bar, one can fork several activities. Later on these concurrent activities can join again by using the same synchronization bar. Both activities and sub-activities can occur concurrently. In the example of Figure 5, Activity 2 and Activity 3 are concurrent ...
The precedence diagram method (PDM) is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes, referred to as nodes, to represent activities and connects them with arrows that show the dependencies. It is also called the activity-on-node (AON) method.