It can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be performed until the predecessor event has occurred. PERT sub-activity: a PERT activity can be further decomposed into a set of sub-activities. For example, activity A1 can be decomposed into A1.1, A1.2 and A1.3.
[2] [3] The PERT distribution is widely used in risk analysis [4] to represent the uncertainty of the value of some quantity where one is relying on subjective estimates, because the three parameters defining the distribution are intuitive to the estimator. The PERT distribution is featured in most simulation software tools.
Program Evaluation and Review Technique, commonly abbreviated PERT, is a statistical tool, used in project management to analyze and represent the tasks involved in completing a given project. PERT network chart for a seven-month project with five milestones (10 through 50) and six activities (A through F).
You are free: to share – to copy, distribute and transmit the work; to remix – to adapt the work; Under the following conditions: attribution – You must give appropriate credit, provide a link to the license, and indicate if changes were made.
For example, a triangular distribution might be used, depending on the application. In three-point estimation, three figures are produced initially for every distribution that is required, based on prior experience or best-guesses: a = the best-case estimate; m = the most likely estimate; b = the worst-case estimate
This determines the shortest time possible to complete the project. "Total float" (unused time) can occur within the critical path. For example, if a project is testing a solar panel and task 'B' requires 'sunrise', a scheduling constraint on the testing activity could be that it would not start until the scheduled time for sunrise. This might ...
It's much less popular than PERT (Program Evaluation and Review Technique) or CPM (Critical Path Method) however, it allows some of those methods limitations to be addressed. The main limitations of PERT or CPM that might be addressed by GERT are: there are no alternative paths - all activities have to be performed
The problem of estimating the maximum of a discrete uniform distribution on the integer interval [,] from a sample of k observations is commonly known as the German tank problem, following the practical application of this maximum estimation problem, during World War II, by Allied forces seeking to estimate German tank production.