The arbitrator who first dealt with Davis Contractors' claim held that "the footing of the contract was removed" and therefore the original contract had come to an end. [1] On referral to the House of Lords, the Lords held that although the performance of the contract had become more onerous, it was not frustrated.
A cost plus contract states that a client agrees to reimburse a construction company for building expenses such as labor, materials, and other costs, plus additional payment usually stated as a percentage of the contract's full price. This type of construction contract is an alternative to lump sum agreements.
Johnson v Gore Wood & Co [2002] 2 AC 1, 49, (a case actually concerning "reflective loss" in UK company law) it was said contract breaking is an ‘incident of commercial life which players in the game are expected to meet with mental fortitude’ Peevyhouse v. Garland Coal & Mining Co., 382 P.2d 109 (Okl. 1962) Tito v Waddell (No 2) [1977] Ch 106
Jacob & Youngs, Inc. v. Kent, 230 N.Y. 239 (1921) is an American contract law case of the New York Court of Appeals with a majority opinion by Judge Benjamin N. Cardozo.The case addresses several contract principles including applying the doctrine of substantial performance in preventing forfeiture and determining the appropriate remedy following a partial or defective performance.
Construction law builds upon general legal principles and methodologies and incorporates the regulatory framework (including security of payment, planning, environmental and building regulations); contract methodologies and selection (including traditional and alternative forms of contracting); subcontract issues; causes of action, and liability, arising in contract, negligence and on other ...
This page was last edited on 23 November 2009, at 17:41 (UTC).; Text is available under the Creative Commons Attribution-ShareAlike 4.0 License; additional terms may apply.
Investors Compensation Scheme Ltd. v West Bromwich Building Society [1997] UKHL 28 is a frequently-cited English contract law case which laid down that a contextual approach must be taken to the interpretation of contracts. Lord Hoffmann set out five principles, so that contract should be construed according to:
Of course, it is fair to say that the factors to be taken into account on an issue of construction, namely the words used in the contract, the surrounding circumstances known to both parties at the time of the contract, commercial common sense, and the reasonable reader or reasonable parties, are also taken into account on an issue of implication.